Dubuque Pipeline Replacement

Dubuque Pipeline Replacement

Energy & Utilities
Procurement
Freeport
IL

Ardmore Roderick is partnered with Price Gregory International to complete the replacement of a 60-mile section of a 70+ year old, 22″ natural gas pipeline for Nicor Gas. The project includes installation of a new 24″ pipeline, main line valves, and distribution stations. Ardmore Roderick’s responsibilities include:

Procurement

  • Material, Equipment, and Execution of subcontracts
  • Vendor Account Setup
  • Issuance of Purchase Orders
  • Weekly invoice processing

Field Services

  • Drawings and specifications analysis
  • Critical reporting
  • Solicitation of subcontracts
  • Monitoring the operation of 16 individual field crews

The first 14 miles of the project was completed ahead of schedule and the team was awarded an additional five miles of work to complete for the first phase of the project.